Premier Tree Services Ltd
All aspects of Commercial and Domestic Tree Care
Pipework & Steelwork Fabrication

Site Clearance

Site clearance projects undertaken by Premier Tree Services:

Turbine Business Park, Sunderland. Paxman Landscapes

Premier Tree Services were contracted to remove a total of 5 hectares of heavy vegetation and 22 mature trees adjacent to the A1231 / A19. This was to make way for a new development of hotels, leisure park and shopping and business facilities.

Phase 1

February 08 - clear vegetation outside of area believed to be occupied by Great Crested Newts - approximately 2 hectares using tractor mounted 300hp mulching unit and excavator with grab.
Works were completed outside of the birds’ nesting season. However, our ecologist was present each day to carry out on site assessments of the area to be worked prior to commencement.

Phase 2

October 08 - Clear remaining 3 hectares of vegetation using 400hp tracked mulching unit. Due to the wet summer months the entire site had become waterlogged and site access and egress was difficult due other contractor now being present on site.

Mulcher picture 1 Mulcher picture 2 Mulcher picture 3

TT2 New Tyne Tunnel (north) Vegetation clearance. Hellens Group

Premier Tree Services were contracted to clear approximately 3 hectares of trees and vegetation from the north side of the new Tyne Tunnel Development at North Shields. The work involved the clearance of some large mature trees adjacent to the A1 / A19 and also required the clearance of 500m of steep roadside embankment.

Tractor & Mulcher working on new Tyne Tunnel clearance project Tractor & Mulcher working on new Tyne Tunnel clearance project